CA1 |
Look into closure time of automated doors and explore whether a manual closure mechanism could be fitted to allow immediate closure if required for security |
Geof Gage |
The question for this was discussed around the possibility of adding a further push button for immediate closing of the door when in the building. We have investigated and this would not be possible to install. The doors are timed to close to meet H&S requirements and an additional push button would not meet the standards. |
Complete |
18.12.2022 |
CA2 |
Send someone out to look at repairs for the bin room lock and fire door in Essex Place |
Grant Ritchie |
The repairs to both the internal fire doors and bin room doors have been completed. |
Complete |
18.01.2023 |
CA3 |
Share internal block inspection report for Highcroft Lodge with Theresa Mackey once surveys completed and finalised |
Geof Gage |
We will be surveying the internal repairs in April with a view to including this on a programme for 2024/25, our current programme is committed. |
Complete |
17.01.2023 |
CA4 |
Look into the missing padlock for the Essex Place bin chute room and why the room is not being cleaned |
Justine Harris |
The room is cleaned after each rubbish collection. The missing padlock has been replaced. |
Complete |
16.01.2023 |
CA5 |
Look into why Theresa Mackey received a letter from the Fire and Rescue Service stating she was responsible for undertaking inspections and checks of Highcroft Lodge |
Geof Gage |
We have raised this with East Sussex Fire & Rescue colleagues, it would appear that this was sent in error and was a mistake on their part. We have asked that ESF&R check that this is isolated and has not been sent to other residents elsewhere in the City. |
Complete |
16.12.2022 |
CA6 |
Look into broken roof tiles and scaffolding plank left at Homestead |
Geof Gage |
We are arranging for contractors to attend and identify the issue and to remove the board and repair as necessary |
Complete |
17.01.2023 |
CA7 |
Someone to be sent out to look at laundry room doors repair in Essex Place |
Geof Gage |
An operative has been sent to look at the laundry room door. Please see the complete response in the questions. |
Complete |
16.12.2022 |
CA8 |
Speak with team to consolidate plan to remedy escalating anti-social behaviour in Essex Place |
Martin Reid |
We ask that all incidents of ASB are reported to our Housing Customer Services Team on 01273 293030. It is really important this happens, as it helps to inform our requests to the security team and whether we need to request additional sweeps.
We have asked our security company to carry out more thorough sweeps of the building. This includes checking the ground floor, the laundry room and the stairwells. Whenever we get an increase in reports of ASB, one of the things we do is look at our security sweep arrangements to determine if additional measures are needed. |
Complete |
20.01.23 |
CA9 |
Email Theresa Mackey the criteria for ‘Dwellings meeting Decent Homes standard’ from Council Housing Performance Report |
Geof Gage |
Require email for Theresa Mackey, the access to the Decent Home standards can be found on the Councils website at this link How we invest in your council homes (brighton-hove.gov.uk) - https://www.brighton-hove.gov.uk/housing/council-housing/how-we-invest-your-council-homes |
Complete |
09.01.2023 |